Construction Update, August 5 - Osauka is OPEN!
Construction Update, August 5 - Osauka is OPEN!
Sauk Rapids-Rice Middle School
- Exterior
- Exterior brick by door six
- Installing new door
- Exterior brick by door six
Sauk Rapids-Rice High School
- The pavement of the south parking lot, parent pick up and drop - DONE
- The south parking lot and Osauka Road are open for use.
- Replacement of Parking Lot lights. -
- Oh hold until September when the light poles arrive
- Theatrical Light in the PAC
- Start-up and testing this week
- 2nd-floor hallway replacement - DONE
- Pavement of Bus Loop -DONE
- Open to the public
Rice Elementary
- Playground
- Poured in Place pathways are scheduled to be installed this week
- Exterior brick and window replacement
- Misc finishing touches and punch list items