Construction Update, July 22
Construction Update, July 22
Sauk Rapids-Rice Middle School
- Exterior
- Exterior brick by door six
- Laying up brick this week
- Exterior brick by door six
Sauk Rapids-Rice High School
- The pavement of the south parking lot, parent pick up and drop - DONE
- Continue to be closed to the public until Osauka Road is complete
- Replacement of Parking Lot lights.
- Dirt work and hydroseeding are being done - ongoing
- Theatrical Light in the PAC
- Installing new equipment - ongoing
Mississippi Heights Elementary
- 2nd-floor hallway replacement - DONE
- Pavement of Bus Loop -DONE
- Open to the public
Rice Elementary
- Playground
- Poured in Place pathways are scheduled to be installed next week
- For everyone's safety during this process, access to the older part of the playground will be temporarily restricted to staff, students, and the public until further notice.
- Exterior brick and window replacement
- Tuck pointing and brick replacement have been completed.
- Finishing windows and sidewalk work this week.