Construction Update, August 12
Construction Update, August 12
Sauk Rapids-Rice Middle School
- Exterior
- Exterior brick by door six -
- Waiting for the grass to be established.
- Exterior brick by door six -
Sauk Rapids-Rice High School
- The pavement of the south parking lot, parent pick up and drop - DONE
- The south parking lot and Osauka Road are open for use.
- Replacement of Parking Lot lights. - ON HOLD
- Oh hold until September when the light poles arrive
- Theatrical Light in the PAC
- Start-up and testing
- 2nd-floor hallway replacement - DONE
- Pavement of Bus Loop -DONE
- Open to the public
Rice Elementary
- Playground
- Waiting for the grass to be established.
- Pavillion waiting for rafters to ship
- Exterior brick and window replacement
- Placing sod and finishing punch list items