Summer Construction Complete, August 29
Summer Construction Complete, August 29
Sauk Rapids-Rice Middle School
- Exterior
- Exterior brick by door six - DONE
Sauk Rapids-Rice High School
- The pavement of the south parking lot, parent pick up and drop - DONE
- Replacement of Parking Lot lights. - ON HOLD
- Oh hold until September when the light poles arrive
- Theatrical Light in the PAC -DONE
- 2nd-floor hallway replacement - DONE
- Pavement of Bus Loop -DONE
Rice Elementary
- Playground - DONE
- Pavillion Completed week of Aug 26
- Exterior brick and window replacement - DONE